Dartford High Street

The works included drainage, kerbing, imported high end paving and planters, surfacing and HFS. WTM were involved from the design stage dealing with vehicle and pedestrian movements through the busy high street.

 

The traffic management that was required for this project was:-

  • 12d Temporary pedestrian crossing
  • 12d Stop Go traffic management
  • Application with local council for the implementation of a TTRO a road closure & diversion
  • Weekday Site maintenance
  • Traffic marshals for site access and egress